|
III. Preparing the
Surface for Installation
1.
Rigid Backwall Installation:
Cover the entire surface area where OCS veneer will be
applied with a weather resistant barrier and install all
necessary flashing.
2. Clean
and Untreated Concrete, Masonry, and Stucco: Check
poured concrete closely, to see if the finished surface
contains any release agents such as form oil. If it
does, acid etch the area and rinse thoroughly as this
will prepare the surface for an adequate bond. No
further preparation needed.
3.
Dirty, Painted, or Sealed Concrete, Masonry and
Stucco: For the stone to
bond, the surface area needs to be free of any foreign
substance such as paint, dirt, or sealers. If these
substances are present, sandblast or water blast until
the area is clean and free of these foreign substances.
If the area cannot be cleaned completely, metal lath can
be nailed to the concrete, masonry, or stucco using
galvanized concrete nails.
4. Metal
Buildings: Apply paper backed metal lath using
adequate galvanized screws over a primary weather
resistant barrier.
IV. Installation
Procedures
1.
Lay Out the Stones: It is
recommended that prior to installation a quantity of
stone should be laid out giving you a good idea of the
shapes, sizes, depths and color pattern. This allows
you to visualize the desired pattern and give you
a selection of stone to choose from. Thick stones
should be place beside thin stone, wide beside narrow,
smooth beside textured. Mix stones from several boxes
to ensure a good blend of sizes and color.
2. Mixing
Mortar: Mortar can be mixed in a mechanical mixer
or by hand. Mortar for OCS stone veneer is mixed very
similar to brick or block mortar, the only difference is
the amount of sand. Mortar for stone has less sand
which gives the mix more Portland cement per unit. This
gives more bonding power to the mortar. The
mortar should be mixed 2 parts sand to 1 part type S
mortar mix, water should be added to obtain the proper
slump.
3. Appling
Metal Lath: The weather resistant barrier, flashing
and metal lath should be applied according to the
directions outlined in section II.
4. Appling
the Scratch Coat: A ½ inch coat of mortar should be
applied to the metal lath using a mason’s or plaster
trowel and allowed to dry. Scratch the surface area to
allow for a good bond when setting the stone.
5.
Setting the Stones: OCS
stone veneer can be installed from the top down, but the
most common method is from the bottom up. A masons
level should be used periodically to ensure the stones
are installed level and plumb. Level chalk line can be
applied to the scratch coat to assist in proper
installation. Completely cover the back surface of the
stone with ¾ inch of mortar and firmly press onto the
prepared wall allowing mortar to squeeze out around the
stones edges. Use trowel to strike off excess mortar
before installing the next piece. All corners have a
long and short side, these should be alternated in
opposite directions as you apply them. To simplify
installation, stone around windows, doors and corner
stones should be installed first.
6.
Consistent Joints: Whether you are doing a dry
stack or a mortar joint application, all joints should
be consistent. Cutting and trimming the stones may be
necessary to achieve the consistent and desired joint.
7.
Cutting and Trimming Stones:
Stones can be cut to obtain the desired
fit, by using a hatchet, nippers or an electric saw with
a diamond blade. Cutting should be done outside using
safety glasses and a dust mask. Cut edge should be
hidden from sight. To conceal the raw edges cover with
mortar when installing. Cut edges should be position
up when above eye level and down when below eye level.
V. Joints and Grouting
Grouting may be necessary
or desired after stone is set in place. Grouting
technique can give the stone many different
appearances. If mortar smears when grouting , allow to
dry and brush with a soft bristled brush. Never use a
wet or a wire brush to remove a mortar smear.
1.
Drystack: Drystacked stone
installation is achieved by stacking the stone with
little or no joint at all. When setting the stone
mortar will seep between the stone, once the mortar is
set, striking the joint with a sharp object will give
the appearance of no joint at all.
2. Standard
Joint: This is achieved by laying each stone
approximately ½ to ¾ inch apart. Once stone is laid,
fill grout bag ½ full of mortar and squeeze mortar into
joint area filling any voids. When the mortar becomes
firm or thumb print dry, it should be pointed up with
a wooden stick or a metal jointing tool. Rake out
mortar to the depth desired. Even joints will give a
professional looking finish.
3. Over
Jointing: This technique is becoming more popular,
giving the stone an old world rustic appearance. The
stone is set similar to the standard joint, however
grouting should overlap the stone, widening the joints
and making them irregular. This technique is used in
the OCS cobble and field stone profiles.
 |